Work Within Right-Of-Way Work Within Right-Of-Way Permit # R2021-043, App. # App-2021-001562, UID # 193870
Status: Approved
Valid: 09/03/2021 - 09/03/2022
 

Applicant

Applicant:
Name:
Nick Kotrba
Phone:
(218689 - 8507
Email Address:
nkotrba@icloud.com
Mailing Address:
36726 160th St NE
Goodridge MN 56725
Work Agreement: Yes
Deposit Agreement: Yes

Contractor

Contractor:
Name:
Nick Kotrba
Company Name:
L N O Kotrba
Daytime Phone Number:
(218689 - 8507
Email Address:
nkotrba@icloud.com
Company Mailing Address:
36726 160th ST NE
Goodridge MM 56725

Work Description

Type of Work:
Ditch Cleaning
Work Description:
Grating ditch bottom and back slope
Work to Start: 09/03/2021

Ditch

Type of Request: Ditch Cleaning
Length: 1 Miles

Site Plan

How many other entrances exist? 0

Location

Road Number: 370
Township: Star
Section: 4
Please mark location of work on the map:

Terms

GENERAL
  • I, We, the undersigned, herewith accept the terms and conditions of the regulations as attached hereto of the Pennington County Highway Department and agree to fully comply therewith to the satisfaction of the Pennington County Highway Department. NO WORK CAN COMMENCE UNTIL APPROVED BY THE COUNTY ENGINEER OF THE PENNINGTON COUNTY HIGHWAY DEPARTMENT.

PURPOSE
  • County Highways are maintained for the movement of vehicles, loads and pedestrians as provided by law. In the interest of public convenience and necessity, circumstances at times makes it desirable to allow individuals and utility companies to sue the highways for other purposes. However, to prevent recurring dangerous and annoying interruptions to traffic on highways, to avoid interference with future highway construction, and to provide common and uniform standards and methods of performance, it is necessary that rigid control be maintained, that standard procedure be followed, and that standard specifications and regulations be enforced through the issuance of permits to authorize all regulated activities of the public within County Highway limits.

SPECIAL REQUIREMENTS
    1. Ditching must follow detail attached.
    2. All materials excavated must be disposed of outside of the County Highway Right of Way, or as the County Engineer directs.
    3. All work must be done in a good workmanship like manner.
    4. All work must be done without any expense to the County.
    5. Other affected landowners, if any, shall be informed and their approval obtained by the applicant and by signing this application the applicant is indicating that he has complied with this requirement.
    6. The Pennington County Highway Department shall be notified of the start of the work for approval.
    7. Applicant needs to get a notification of approval before starting work.
    8. Permit is good for one year from date of approval.
APPLICATION FOR DITCHING WORK IN ROW
    1. The attached entrance and ditching design standards have been developed to serve as a guide in the construction of entrances. Applicants will be required to use these designs. Department inspects site, order corrective work if necessary, and returns deposit upon satisfactory completion of work.
    2. A monetary deposit of $500.00 per mile is required and will be returned upon satisfactory completion of the work.
    3. There is no initial applicant fee although there is an After the Fact fee of $500.00 a mile fee.

Invoice #43683 (09/02/2021)

Charge Cost Quantity Total
Grand Total
Total $0.00
Due$0.00

Approvals

ApprovalSignature
ApplicantNick J. Kotrba - 09/02/2021 2:28 PM
35670b3f797ae9d296a5e7e4f0d5971b
2b6cdd6f3cb083cdadd5a3a8b0e86769
#1 County Highway EngineerJoe P. Garry - 09/02/2021 3:45 PM
c9dda42a96375b415dc76781374e35d7
e327ff146ef50a6ecd28964c9bf32307
Application has been approved. All signatures have been obtained.
Powered by